The 7 following technical points must be completed at your customer’s premises for a successful installation:

A dedicated cold water rising main water supply, within 2 meters of the cooling unit.

2 dedicated 13A switched electrical power sockets (no extension leads) located within 2 meters of the cooling unit (cord length)

A water drain is recommended

A well ventilated room with a temperature below 30 degrees

Accessibility to the installation room: if not on the ground floor/in a basement, presence of a lift or a staircase wide enough to deliver the cooling unit

Ductwork safely accessible for the technician, to run python from the cooler to the dispense head

Compliance with the space constraint around the cabinet: + 20cm on the left for the CO2 cylinder + 1m in front of the cabinet for technical operations and replacing the BIB.

• Standard Bag in box rack cabinet dimensions (without cooling unit): W680 x D440 x H720

• Standard Bag in box rack cabinet dimensions (with cooling unit): W680 x D440 x H1500

ABOUT OUR POSTMIX

GOOD TO KNOW drilling of the walls to run the duct between the cooling unit/technical room and the dispenser/bar gun is under the responsibility of the customer.

CCEP 2024 EQUIPMENT PORTFOLIOCCEP 2024 EQUIPMENT PORTFOLIOCCEP 2024 EQUIPMENT PORTFOLIOCCEP 2024 EQUIPMENT PORTFOLIOCCEP 2024 EQUIPMENT PORTFOLIOCCEP 2024 EQUIPMENT PORTFOLIOCCEP 2024 EQUIPMENT PORTFOLIOA COMPETITIVE ADVANTAGEA COMPETITIVE ADVANTAGECONTACT USCONTACT USCONTACT USCONTACT USESSENTIAL ACTIONS WITH YOUR CUSTOMERSESSENTIAL ACTIONS WITH YOUR CUSTOMERSOUR COMMITMENTSOUR COMMITMENTSRULES FOR OUTDOOR VENDOR PLACEMENTRULES FOR OUTDOOR VENDOR PLACEMENTECO-FRIENDLY EQUIPMENTECO-FRIENDLY EQUIPMENTOPERATIONAL BEST PRACTICEOPERATIONAL BEST PRACTICEOPERATIONAL BEST PRACTICEOPERATIONAL BEST PRACTICEESSENTIALS ACTIONS WITH YOUR CUSTOMERSESSENTIALS ACTIONS WITH YOUR CUSTOMERSOUR COMMITMENTSOUR COMMITMENTSTHE LITTLE COCA COLA FACTORYTHE LITTLE COCA COLA FACTORYBEHIND THE SCENE OF POSTMIX INSTALLATIONSBEHIND THE SCENE OF POSTMIX INSTALLATIONSBEHIND THE SCENE OF POSTMIX INSTALLATIONSBEHIND THE SCENE OF POSTMIX INSTALLATIONSOPERATIONAL BEST PRACTICEOPERATIONAL BEST PRACTICEOPERATIONAL BEST PRACTICEOPERATIONAL BEST PRACTICECORE RANGE PRODUCTSCORE RANGE PRODUCTSSINGLE DOOR COOLERSSINGLE DOOR COOLERSSINGLE DOOR COOLERSSINGLE DOOR COOLERSSINGLE DOOR COOLERSSINGLE DOOR COOLERSSINGLE DOOR COOLERSSINGLE DOOR COOLERSDOUBLE DOOR COOLERSDOUBLE DOOR COOLERSDOUBLE DOOR COOLERSDOUBLE DOOR COOLERSCOUNTER TOP & BACK BAR COOLERSCOUNTER TOP & BACK BAR COOLERSCOUNTER TOP & BACK BAR COOLERSCOUNTER TOP & BACK BAR COOLERSCOUNTER TOP & BACK BAR COOLERSCOUNTER TOP & BACK BAR COOLERSCOUNTER TOP & BACK BAR COOLERSCOUNTER TOP & BACK BAR COOLERSIMPULSE COOLERSIMPULSE COOLERSIMPULSE COOLERSIMPULSE COOLERSIMPULSE COOLERSIMPULSE COOLERSIMPULSE COOLERSIMPULSE COOLERSIMPULSE COOLERSIMPULSE COOLERSVENDORSVENDORSVENDORSVENDORSVENDORSVENDORSVENDORSVENDORSVENDORSVENDORSVENDORSVENDORSVENDORSVENDORSPOSTMIXPOSTMIXPOSTMIXPOSTMIXPOSTMIXPOSTMIXPOSTMIXPOSTMIXPOSTMIXPOSTMIXPOSTMIXPOSTMIXPOSTMIXPOSTMIXPOSTMIXPOSTMIXPOSTMIXPOSTMIXPOSTMIXPOSTMIXMONSTER COOLERSMONSTER COOLERSMONSTER COOLERSMONSTER COOLERSMONSTER COOLERSMONSTER COOLERSMONSTER COOLERSMONSTER COOLERSMONSTER COOLERSMONSTER COOLERSMONSTER COOLERS