Location
Annacis Island, British Columbia
Client
Metro Vancouver
Delivery
2019 2023
Contract type
Lump sum, in partnership
Project
As part of a major upgrade of the wastewater treatment facilities, build a new outfall system to meet the needs of a growing population and safely release treated wastewater into the Fraser River. The plant treats about 175 billion litres of waste- water every year.
Challenges
Technically complex project: Construct two tun- nels for a total of 820 metres, two 40-metre deep on-land shafts and a marine diffuser in the Fraser River.
Ensure the outfall system operates in the event of an earthquake.
Solution
Use a tunnel-boring machine which will be assem- bled and launched in one of the two vertical shafts, and lifted when the tunnels are excavated in the second shaft.